Dixons Newhall Green Academy, Wythenshawe

SCS successfully secured and delivered the EOS Remagin SFS, with Promat/Etex fireboarding encasements of steel, Siniat drylining and internal partitions, plastering, Rockfon suspended ceilings and acoustic wall panel packages.

Main Contractor

Morgan Sindall Construction North West

Contract Date

February 2025- August 2025

SCS Contract Value

£2.1m Over a 39 Week

Period

Supply Chain Distribution

Galaxy, Minster

Architect

IBI Group – Intelligence Buildings Infrastructures

Team

Alan Spence, Will Clerehugh, Craig Scott

Contact Us.

Head Office:
Newmarket Mews
Aberford Road
Stanley
Wakefield. WF3 4AL

Head Office Tel:
0113 288 7111

General Enquiries:
enquiries@scs-north.com

Accounts Department:
accounts@scs-north.com

Key Contact:
Paul Flynn – Operations Director
paul@scs-north.com

SCS Group Newsletter

Register to receive news and industry updates.

SCS Building Solutions Ltd | Registered in England No. 2893518

Scroll to Top